Time-Cost-Quality Tradeoff Modeling based on Resource Allocation

Decision Variables and Assumptions

Relationship between Construction Administration Quality and Administration Cost

A construction team consisting of sufficient crew members could improve construction quality and consume a reasonable cost, but the construction team hardly impacts on construction productivities. Therefore it is assumed that administration cost and administration quality are an approximate linear function:

AC(i)=ACmini+AQKi×(AQ(i)AQmini)        (7)

where AQ(i)= actual quality level of construction administration (i) in activity (i), AQ(i)(AQmini,AQmaxi);AQmini= minimum quality level of construction administration (i) in activity (i);AQmaxi= maximum quality level of construction administration (i) in activity (i);AQKi=(ACmaxiACmini)/(AQmaxiAQmini);

ACmini= minimum cost of construction administration (i) in activity (i);

ACmaxi= maximum cost of construction administration (i) in activity (i);

AC(i)= actual cost of construction administration (i) in activity,

AC(i)(ACmini,ACmaxi).

Since work overtime might increase administration cost, the construction administration cost will be modified by factor βi:

AC(i)=[ACmini+AQKi×(AQiAQmini)]×βi=[AC(i)=ACmini+AQKi×(AQ(i)AQmini)]×[ACRKi+1ACRKiDPK(i)],   (8)

where βi= administration cost modification factor during work overtime because of extra or additional construction equipment, βi=ACRKi+(1ACRKi)/DPK(i); ACRKi= administration hourly cost rate factors in activity (i) when overtime working is applicable, usually 2.0.