Time-Cost-Quality Tradeoff Modeling based on Resource Allocation
Decision Variables and Assumptions
Relationship between Construction Administration Quality and Administration Cost
A construction team consisting of sufficient crew members could improve construction quality and consume a reasonable cost, but the construction team hardly impacts on construction productivities. Therefore it is assumed that administration cost and administration quality are an approximate linear function:
AC(i)=ACmini+AQKi×(AQ(i)−AQmini) (7)
where AQ(i)= actual quality level of construction administration (i) in activity (i), AQ(i)∈(AQmini,AQmaxi);AQmini= minimum quality level of construction administration (i) in activity (i);AQmaxi= maximum quality level of construction administration (i) in activity (i);AQKi=(ACmaxi−ACmini)/(AQmaxi−AQmini);
ACmini= minimum cost of construction administration (i) in activity (i);
ACmaxi= maximum cost of construction administration (i) in activity (i);
AC(i)= actual cost of construction administration (i) in activity,
AC(i)∈(ACmini,ACmaxi).
Since work overtime might increase administration cost, the construction administration cost will be modified by factor βi:
AC(i)=[ACmini+AQKi×(AQi−AQmini)]×βi=[AC(i)=ACmini+AQKi×(AQ(i)−AQmini)]×[ACRKi+1−ACRKiDPK(i)], (8)
where βi= administration cost modification factor during work overtime because of extra or additional construction equipment, βi=ACRKi+(1−ACRKi)/DPK(i); ACRKi= administration hourly cost rate factors in activity (i) when overtime working is applicable, usually 2.0.