Time-Cost-Quality Tradeoff Modeling based on Resource Allocation
Formulating PTCQTP Model
Calculating Overall Time in Construction Project
The overall time of a construction project can be easily calculated by nodes as activities in an acyclic digraph network:
where overall time in construction project,
, as well as the earliest starting time of activity
derived by its predecessors, and the first
.