Mixed Assembly Line Balancing
Assembly lines are meant to be a cost-efficient way to manufacture an item through standardization. Balancing the assembly line allows for low-volume, made-to-order production up to high-volume, mass-produced items. Essentially, balancing the assembly consists of allocating or reallocating tasks to a workstation to minimize downtime or constraints.
Read this article. The article proposes balancing production lines to attenuate capacity restrictions and increase balancing efficiency. Pay particular attention to section 2.2 on assembly line balancing.
Results and discussion
The method was applied in a AL belonging to a manufacturer of agricultural machines of the type drawn with unit manufacturing lot. The AL is organized into five workstations; in each station there is an operator. Moreover, among the workstations there is a buffering unit that has the function of absorbing excess processing time for some models about the cycle time. Figure 9 illustrates the AL current flow, with the number of workstations within the marked blocks and buffers marked with "x" in the center. All computational procedures were performed in spreadsheet.
Figure 9 AL flowchart with current balance. Source: The authors.
The AL in study manufactures seven models of products, called CL, O, MX, CB, ATI, ATU and CH, which are assembled through up to 29 different tasks depending on the model. Table 1 shows the product models, the tasks of each workstation and the precedence relationship.
Table 1 Performed tasks in the AL for each modelthe current AL workload is shown in Figure 10, with the times (in minutes) per workstation and model.
Work station | Taks | Description | Precedence | CL | O | MX | CB | ATI | ATU | CH |
---|---|---|---|---|---|---|---|---|---|---|
1 | 1 | Introduce pre-assembly | - | X | X | X | X | X | X | X |
1 | 2 | Preassemble servostat | 1 | X | X | X | X | X | X | |
1 | 3 | Mount Steering Column | 1 | X | X | X | X | X | X | |
1 | 4 | Preassemble reservoir | 1 | X | X | X | X | X | X | |
2 | 5 | Preassemble accelerator pedal | 1 | X | X | X | X | X | X | |
2 | 6 | Place preassembly device at post | 2;3;4;5 | X | X | X | X | X | X | X |
2 | 7 | Preassemble the console structure | 6 | X | X | X | X | X | X | X |
2 | 8 | Preassemble servostat at column | 7 | X | X | X | X | X | X | |
2 | 9 | Pre-mount clutch cable | 7 | X | X | X | X | X | X | |
2 | 10 | Pre-mount brake pedals support | 7 | X | X | X | X | X | ||
2 | 11 | Mount Valve Brake POWERFILL - 40Km | 7 | X | ||||||
2 | 12 | Mount brake valve and reservoir | 10 | X | X | X | X | X | ||
2 | 13 | Pre-mount brake sensor | 12 | X | X | X | X | X | ||
2 | 14 | Mount switch differential lock | 7 | X | X | X | X | X | X | X |
2 | 15 | Mount clutch pedal | 9 | X | X | X | X | X | X | |
3 | 16 | Mount accelerator pedal | 7 | X | X | X | X | X | X | X |
3 | 17 | Pre-mount plugs from the brake lines | 11;12 | X | X | X | X | X | X | X |
3 | 18 | Mount Steering Column on the console | 8 | X | X | X | X | X | X | |
3 | 19 | Assemble Hydraulic Hoses Direction | 18 | X | X | X | X | X | X | X |
4 | 20 | Assemble hoses servostat | 8 | X | X | X | X | X | X | X |
4 | 21 | Assemble hose and return pipe | 20;18 | X | X | X | X | X | X | |
4 | 22 | Mount servostat hoses clamp | 21 | X | X | X | X | X | X | X |
4 | 23 | Assemble steering wheel on the console | 18 | X | X | X | X | X | X | X |
4 | 24 | Plase devide in horizontal position | 21 | X | X | X | X | X | X | X |
5 | 25 | Mount firewall plate | 24 | X | X | X | X | X | X | X |
5 | 26 | Mount firewall nuts clips | 25 | X | X | X | X | X | X | X |
5 | 27 | Seal outside on the console | 26 | X | X | X | X | X | ||
5 | 28 | Plase devide upright | 27 | X | X | X | X | X | X | X |
5 | 29 | Final test | Todas | X | X | X | X | X | X | X |
As can be seen in Figure 10, only the stations 3 and 5 have ability to 37 product/shift for any product, since the time all product models is less than the cycle time. Currently, AL capacity at bottleneck situation is 28 products per shift.
Table 2 presents the mix of products using the company's production plan and the proportion of each model calculated from Equation 8.
PRODUCT MODEL | Τ | |||||||
---|---|---|---|---|---|---|---|---|
CL | O | MX | CB | ATI | ATU | CH | ||
MIX
(quantify for model) |
0.8 | 1.2 | 0.4 | 12.5 | 1.7 | 20.0 | 0.4 | 37.0 |
Proportion of model | 2% | 3% | 1% | 34% | 4% | 54% | 1% | 100% |
Table 3 shows the time weighted average processing for each task and the RPW for each task calculated using Equation 9.
After increasingly ordering the tasks in accordance with the value of the RPW, it was determined the number of the last workstation (W). To do this, we calculated the minimum number of workstations for each model (Equation 12), and then it was defined as a worst case model with higher MinW (in this case, the ATU model, according to Table 4).
PRODUCT MODEL | |||||||
---|---|---|---|---|---|---|---|
CL | O | MX | CB | ATI | ATU | CH | |
CTTm | 46.0 | 51.6 | 39.6 | 62.1 | 56.8 | 66.3 | 52.3 |
TC | 12.97 | 12.97 | 12.97 | 12.97 | 12.97 | 12.97 | 12.97 |
MinW | 3.55 | 3.98 | 3.06 | 4.79 | 4.38 | 5.11 | 4.03 |
6 | |||||||
W=j | 6 |
PRODUCT MODEL | ||||||||
---|---|---|---|---|---|---|---|---|
CL | O | MX | CB | ATI | ATU | CH | ||
MinW | 6 | 6 | 6 | 6 | 6 | 6 | 6 | |
CTTm | 46.0 | 51.6 | 39.6 | 62.1 | 56.8 | 66.3 | 52.3 | |
j = 6 | CTAj+1 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
AVMm | 7.7 | 8.6 | 6.6 | 10.3 | 9.5 | 11.0 | 8.7 | |
j = 5 | CTAj+1 | 8.4 | 8.5 | 10.6 | 10.8 | 10.8 | 10.8 | 10.8 |
AVMm | 7.5 | 8.6 | 5.8 | 10.3 | 9.2 | 11.1 | 8.3 | |
j = 4 | CTAj+1 | 18.2 | 18.2 | 16.2 | 20.5 | 22.0 | 22.0 | 22.3 |
AVMm | 7.0 | 8.3 | 5.9 | 10.4 | 8.7 | 11.1 | 7.5 | |
j = 3 | CTAj+1 | 23.5 | 23.6 | 24.1 | 33.2 | 29.9 | 29.9 | 31.3 |
AVMm | 7.5 | 9.3 | 5.2 | 9.6 | 9.0 | 12.1 | 7.0 | |
j = 2 | CTAj+1 | 31.5 | 31.5 | 26.9 | 41.4 | 38.2 | 42.4 | 35.6 |
AVMm | 7.3 | 10.1 | 6.4 | 10.4 | 9.3 | 11.9 | 8.4 | |
j = 1 | CTAj+1 | 33.6 | 39.2 | 35.3 | 49.7 | 44.4 | 53.9 | 44.0 |
AVMm | 12.3 | 12.3 | 4.4 | 12.3 | 12.3 | 12.3 | 8.4 |
Workstation | Task |
---|---|
1 | 1; 2; 4; 5 |
2 | 3; 6; 7; 14 |
3 | 8; 9; 10; 12; 16; 18 |
4 | 11; 15; 20; 23 |
5 | 13; 17; 19; 21 |
6 | 22; 24; 25; 26; 27; 28; 29 |
Current balancing | New balancing | ||
---|---|---|---|
VARIABLE | Time available in the period p (min) | 480 | 480 |
Demand (parts) | 37 | 37 | |
Cycle time (min) | 12.97 | 12.97 | |
Number of buffers | 4 | 0 | |
Model bottleneck | ATU | CB | |
Tg (min) | 17.12 | 12.69 | |
CTTg (min) | 66.3 | 62.1 | |
INDICATOR | Amount of AL workstations | 5 | 6 |
Capg (parts) | 28.0 | 37.8 | |
TCestimg (min) | 154.08 | 76.14 | |
Line efficiency bottleneck situation (LEg) | 63% | 83% | |
Balancing efficiency (BE) | 85% | 94% |
The results presented in Table 6 indicate significant improvements from the point of view of the company's experts. The ability of 37 products/shift exceeded the capacity index of the current state by 35% for the AL bottleneck model. This increase is due to the new distribution of tasks. Furthermore, the new balancing allows the release of the products in AL without particular sequence, which gives great flexibility to the system.
The crossing time estimated in the bottleneck situation was reduced by 50%, which represents that a product can reach the customer 78 minutes faster than today. Finally, the line Efficiency bottleneck situation showed an improvement of 32% under the influence of reduction in processing time bottleneck station (due to rebalance). The balancing efficiency improved 11% (from 85% to 94%), resulting in a better balanced distribution of tasks between the workstations about to the current balance.
Finally, a comparison was performed between the resulting RPW-MVM balancing against traditional RPW applied to mixed-AL, according to Table 7. The flexibility of precondition for a demand for 37 products per shift was not met for the case of balancing proposed by traditional RPW, as capacity in the bottleneck situation was 31.4 products/ shift. Moreover, a reduction in line efficiency at bottleneck situation was observed, despite the reduction of a workstation having occurred, along with the increase in 4% balancing efficiency.
New balancing
RPW-MVM |
New balancing RPW | ||
---|---|---|---|
VARIABLE | Time available in the period p (min) | 480 | 480 |
Demand (parts) | 37 | 37 | |
Cycle time (min) | 12.97 | 12.97 | |
Number of buffers | 0 | 0 | |
Model bottleneck | CB | CH | |
Tg (min) | 12.69 | 15.28 | |
CTTg (min) | 62.1 | 52.32 | |
INDICATOR | Amount of AL workstations | 6 | 5 |
Capg (parts) | 37.8 | 31.4 | |
TCestimg (min) | 76.14 | 76.38 | |
Line efficiency bottleneck situation (LEg) | 83% | 82% | |
Balancing efficiency (BE) | 94% | 98% |