Time-Cost-Quality Tradeoff Modeling based on Resource Allocation

Read this article. The paper presents an optimization model that enables managers to effectively evaluate trade-offs related to time, cost, and other competing priorities. Pay particular attention to Section 6 as it provides an illustrated example of building a home.

Abstract

The time, quality, and cost are three important but contradictive objectives in a building construction project. It is a tough challenge for project managers to optimize them since they are different parameters. This paper presents a time-cost-quality optimization model that enables managers to optimize multiobjectives. The model is from the project breakdown structure method where task resources in a construction project are divided into a series of activities and further into construction labors, materials, equipment, and administration. The resources utilized in a construction activity would eventually determine its construction time, cost, and quality, and a complex time-cost-quality trade-off model is finally generated based on correlations between construction activities. A genetic algorithm tool is applied in the model to solve the comprehensive nonlinear time-cost-quality problems. Building of a three-storey house is an example to illustrate the implementation of the model, demonstrate its advantages in optimizing trade-off of construction time, cost, and quality, and help make a winning decision in construction practices. The computational time-cost-quality curves in visual graphics from the case study prove traditional cost-time assumptions reasonable and also prove this time-cost-quality trade-off model sophisticated.



Source: Wenfa Hu and Xinhua He, https://www.hindawi.com/journals/tswj/2014/673248/
Creative Commons License This work is licensed under a Creative Commons Attribution 3.0 License.