Lag and Lead Times
Most
activities in a network diagram have a finish-start relationship. If a
certain amount of time must go by before a successor activity can begin,
the required delay is called lag time.
For example, concrete does not reach its full strength for several
days
after it is poured. Lag time is required between the end of the
pouring
process and the beginning of construction that puts stress on the
concrete as diagrammed in Figure 8.10. Similarly, you must allow lag
time for payment checks to be processed by the banking system before
you can spend the money.
Figure 8.10 Required time between activities is lag time.
In some cases, the successor activity can overlap the end of its predecessor activity and begin before the predecessor is finished. This is called lead time.
Lead Time in John's Move
In John's move, you might begin separating the small and delicate items that will be packed in step 2.3 before you get the packing materials in step 2.1 so that when the materials are available, step 2.3 is already partially completed. If the preparing the small items for packing can overlap its predecessor and shortens the time it takes to accomplish both tasks by a day, it has a lead time of one day. Overlap is called the lead time of the successor activity.
Figure 8.11 The characteristics and identifiers of an activity are its attributes.
At
this point in the process of analyzing John's move, each activity has an
identifying code, a short description, predecessors, and lead or lag
times, as shown in a partial table of activities in Figure 8.12 Table of Attributes.
Code | Description | Predecessors | Relationships | Lead/Lag |
---|---|---|---|---|
1a | Contact Dion and Carlita | None | 0 | |
1b | Host planning lunch | 1a | FS (Finish/Start) | 0 |
1c | Develop and distribute schedule | 1b | FS | 0 |
1d | Make hotel arrangement in Atlanta | 1a | FS | 0 |
2a | Gather packing material | None | 0 | |
2bi | Contact moving van companies and get three bids | 1c | FS | 0 |
2bii | Select company and get final price | 2bi | FS | 0 |
2biii | Sign moving contract | 2bii | FS | 0 |
2c | Pac small and delicate items | 1c and 2a | FS and FS | 1 |
Figure 8.12 Table of Attributes